Chapel & Office Renovation: Project Momentum July Update
Dear Northwest Baptist Church Family,
As we continue through the summer, we’re grateful to share several encouraging milestones in our Chapel and Office Renovation Project. Thank you for your continued prayers, generosity, and enthusiasm as we move forward together.
Several important accomplishments have taken place since our last update: A new water shut-off valve has been installed, allowing us to stop the current leak in the Chapel and Office building until a more permanent fix is made. The roofing contractor has been selected, and roofing work is scheduled to begin July 27. The HVAC replacement is scheduled to begin July 21, another significant step toward completing our critical infrastructure improvements. We are also obtaining quotes for a new exterior sign, which will enhance the appearance and visibility of our campus. These are exciting milestones, and we remain thankful that the project continues to move forward on schedule.
Thank you for continuing to invest in the future ministry of Northwest Baptist Church. Since launching Project Momentum, we have already received four additional gifts this summer. Every gift, whether large or small, helps us maintain the momentum God has provided and strengthens our preparation for the next phase of this journey.
This summer’s construction is preparing us for an exciting season in the life of Northwest Baptist Church. While our immediate focus is on completing these important facility improvements, our Leadership Team is also prayerfully preparing for the next phase of our capital campaign, which will officially launch in October.
In the months ahead, we’ll begin sharing more of the vision for what lies beyond these initial repairs and how God may use these facilities to strengthen ministry for years to come. For now, we simply ask you to continue praying for wisdom, unity, and God’s direction as we take each step together.
Please continue praying for the contractors, our leadership team, and everyone involved in the project. We are grateful for God’s continued provision and for the unity He has created within our church family.
As promised, we’ll continue providing monthly Project Momentum updates so you can celebrate the progress, stay informed, and join us in praying for what God is doing through Northwest Baptist Church.
Together, we continue to pursue our mission of intentionally growing to be made more like Jesus.
With gratitude,
The Leadership Team
Northwest Baptist Church
Chapel & Office Renovation Q&A
Project Overview
Why are we undertaking this project now?
Our current Chapel and Office building is 66 years old (planted in 1957, built in 1959). It was built to a Texas design that is not suited for the Wisconsin climate. Key systems, including the roof and HVAC, have served far beyond their intended life and now require urgent attention to preserve the facility’s integrity.
Is this only about a roof?
No. The leadership team was charged to look beyond just fixing a roof. The goal is to align our facilities with the mission God has given Northwest Baptist Church (NWBC) right now. We are evaluating how this facility can best serve our current ministry needs and our Kingdom Partners.
Who are our Kingdom Partners?
We currently share our space with several partners who are more than just tenants; they are part of the work God is doing here:
– Word of Hope Community Church
– Desire of All Nations Church
– Christian Youth Theater
The Phased Plan
What was the motion approved in February 2026?
The church authorized a two-phase approach to the renovation of the Chapel Office Building to ensure wise stewardship and financial responsibility.
What is Phase 1?
Phase 1: Immediate Repairs
Goal: Raise approximately $80,000.
Scope: Repair and replacement of the Roof and HVAC systems.
Status: 5-week campaign “sprint” complete. Contractors have been selected. Scheduling the repairs is underway, and construction should begin soon.
What is Phase 2?
Phase 2: Capital Campaign & Interior Renovation
Goal: A total project goal of $450,000 (meaning an additional ~$370,000 after Phase 1).
Scope: Interior improvements, furnishings, and non-critical construction.
Contingency: Construction for Phase 2 is strictly contingent upon the pledges and receipts of the formal Capital Campaign.
How can I give?
Place gifts in the offering box at the back of the sanctuary or contribute online through our website. Please write “Project Momentum” on the memo line (checks) or select Project Momentum in the dropdown menu if giving online.